HSE - September 2026
3 MLD Desalination Project site, V.O. Chidambaranar Port, Tuticorin | September 2026
An Onsite Job-Specific Training Programme was conducted at the 3 MLD Desalination Project, VOC Port, Tuticorin, to strengthen workplace safety awareness and promote safe lifting and material-handling practices among project personnel.
The training focused on identifying potential hazards associated with lifting operations, ensuring the proper use of lifting equipment, and reinforcing compliance with applicable safety procedures. Special emphasis was placed on equipment inspection, safe operating practices, and accident prevention during lifting and rigging activities.
Key Topics
- Lifting safety and hazard identification
- Safe lifting techniques and procedures
- Third-party inspection of lifting tools and tackles
- Crane and Hydra operation safety
- Rigging and slinging safety practices
- Safe Working Load (SWL) and load capacity assessment
- Pre-use inspection of lifting equipment